Demolition of a building complex for Kalynivka Logistics Center.
Tuesday, 15 January 2008 00:00
kalin1Demolition work began on the building complex, followed by cleanup of the jobsite for construction of the largest logistics center in Kalynivka. The jobsite area is 5 hectares. There are 27 objects scheduled for demolition in total: boiler rooms, warehouses, production facilities, 60-meter chimneys, ramps, and utilities and communication lines. 40 chemical liquid and black oil reservoirs will be processed for re-use. Amount of recycled waste will be 23,500 m3. Employer will use the processed demolition waste right on the jobsite to fill roadbeds and construction site base.